Canonical policy ask · Compute & energy

Pause new large AI data centres pending resource and security review

Pause construction or upgrading of covered AI data centres until Congress enacts specified safeguards and expressly terminates the moratorium.

Current standingintroduced

Jurisdiction map

Current legal position

Policy vehicles

Where the ask appears

Policy lineage

Events and deadlines
  1. 2026-06-24
    AI Data Center Moratorium Act introduced in the House

    H.R. 9442 was introduced and referred to House committees.

Evidence ledger

Explained source passages

H.R. 9442 proposes a conditional moratorium on AI data centres

The bill would stop construction or upgrading of covered facilities until specified safeguards are enacted and Congress expressly ends the pause.

The construction or upgrading of new or existing artificial intelligence data centers may not commence or proceed until—
Congress.gov · H.R. 9442 · Section 3(b)

H.R. 9442 would require quarterly public infrastructure reporting

The bill directs the Energy Secretary to publish facility-level information on water, energy, emissions, labour and other impacts.

The Secretary of Energy shall— (A) submit to Congress quarterly reports on artificial intelligence data centers; and (B) make those quarterly reports publicly available.
Congress.gov · H.R. 9442 · Section 3(c)(1)

IEA reports data-centre electricity demand grew 17% in 2025

The IEA executive summary states global data-centre electricity demand grew 17% in 2025 and AI-focused centres grew 50%.

The global electricity demand of data centres – the critical infrastructure for training and running AI models – grew by 17% in 2025, in line with IEA projections. Electricity consumption from AI-focused data centres grew even faster, surging 50% in 2025.
International Energy Agency · IEA Key Questions on Energy and AI · Executive summary